Kitchen and Bath Remodel: Brooklyn

E-Mail to a Friend

This project was completed August 2009

May 18, 2009

The front elevation of the Burns Park
Colonial. On the exterior, we will
be adding a new portico over the
front porch and a deck to the rear

The existing galley kitchen will be
renovated and relocated, creating
space for a new half-bath

This second floor bathroom will
be updated with new fixtures,
cabinetry, and finishes

June 1, 2009

The kitchen demolition has begun,
with the removal of the fixtures,
countertop and plaster.

This wall between the kitchen and
the dining room will be removed
in order to create a more unified space.

Old tub and tile were removed.
New tub is waiting for new tile

June 15, 2009

The new back door has
been installed, giving Brian
a reason to smile.

The rough framing for the new
half-bath is complete along
with new walls around the stairs.

On the outside, the new air conditioner
has been installed. Work has
begun on the new deck.

June 24, 2009

Phillip (lead carpenter) is on
the phone, coordinating
with a subcontractor.

Drywall has been installed
and the interior spaces
have taken shape.

Brian and Ryan installing new
siding, infilling where an existing
door and window were located.

July 14, 2009

The new dynamic and vibrant
paint colors add energy and
excitement to the entire house.

The kitchen cabinets and countertops
have been installed. Brian is preparing
the space for floor tile installation.

Upstairs, the bathroom vanity and
countertop have also been installed.

July 28, 2009

In the upstairs bathroom,
the tile has been installed
around the shower.

The tile continues around
the room as a wainscot.

Downstairs in the kitchen,
the mosaic tile backsplash
has been installed.

Up close, the tiles show
off their iridescent beauty.

August 3, 2009

A new front door has
been installed. Next
step is the portico.

Phillip is building temporary
supports to hold the portico
while it is being installed.

Here is the portico after being
lifted into place, ready for the
columns and detail work.

August 27, 2009

Our happy home owners are
excited to move into their
house in the next few days.

brooklyn-exterior-finished Here is the finished exterior,
with landscaping in place.

brooklyn-finished-kitchen Looking at the new kitchen,
with the half-bath beyond.

brooklyn-finished-dining Standing in the living room, with
a view toward the new dining space.

brooklyn-finished-bath Upstairs is the finished bath,
bright and cheerful.