Skip page content

Kitchen Remodel: Polo Fields

This project was completed in October 2010.

E-Mail to a Friend

July 12, 2010

 

pf-overall

We are renovating this kitchen, updating
the finishes, the layout, and the applicances.

pf-falling-cabinets

As the current ones are literally falling off the wall, we’ll
be installing brand new painted wooden cabinetry.

pf-mudroom

We’ll also be updating the laundry/mudroom,
with a better layout and storage cubbies.

pf-office

Finally, the office will receive a custom designed, built-in bookcase.

July 26, 2010

pf-demo-complete

Demolition is progressing, with all of the
kitchen cabinets having been removed.

pf-elev-rangepf-elev-sink

These elevations show the new cabinet layout,
adding more drawers for better storage.

pf-demo-mud

Demolition is also continuing in the mudroom.

pf-mud-elev

The new mudroom will have storage cubbies and better shelving.

August 4, 2010

pf-dustdoor

Dust protection in the tall front entry, a small
plastic box out with a zippered door. This keeps
dust in “our” side and keeps it out of “their” side.

pf-pexpipe

The existing house was built with PEX plastic piping for all hot and cold
water. Though this saved money initially, it is susceptible to pitting at
the copper fittings, and several leaks developed in this home.

pf-demo-pipe

All new copper piping is being installed in the house. We
needed to open up the drywall wherever there was old
plastic piping and where new copper piping was to go.

pf-dustwall

Drywall paths along the ceiling and walls in the basement
were removed, and lots of dust protection was set up.

pf-newpipe

New copper is visible, feeding water around the house.

August 17, 2010

pf-drywall1

New drywall is being installed where needed, while the
existing is inspected and repaired as necessary. The goal
is to have a uniform finish throughout the new kitchen.

pf-drywall2

In the basement, we are doing local repairs to patch
areas opened up for plumbing piping replacement.
Here, the idea is to have as minimal impact as possible.

pf-drywall-fin

The drywall in the main kitchen area is completed.
Next steps are refinishing the floor and painting the walls.

August 25, 2010

pf-finish-floor

The kitchen floor has been refinished. We’ll take extra
care to protect it during the rest of the project.

pf-paint

The kitchen is being painted. Areas without
new paint will be covered by the cabinets,
the crown and the tile backsplash.

pf-cab-brian

Brian has moved all the cabinets into the kitchen.

pf-cab-install

The first run of cabinets are in place and
being leveled, adjusted and installed.

September 10, 2010

pf-0910-mudroom-cab

Mudroom cubbies are being installed. They will allow
more storage and easier access than original closet.

pf-0910-kitchen-cab-ref

Cabinets are finished, ready for crown, countertop and backsplash.

pf-0910-kitchen-hood

New stainless steel hood with improved venting and lighting at the range.

September 23, 2010

The granite countertop is being installed.

Followed by the tile backsplash installation.

New stacking washer and dryer save space in the new layout.

September 30, 2010

Here you can see the countertop and tile backsplash at the stove.

View from the other side of the kitchen.

October 4, 2010


The finished kitchen.

Stainless steel appliances contrast with the deep brown backsplash.

Beautiful painted white cabinets compliment the granite countertop.

A cherry cabinet completes the spaces.

 

E-Mail to a Friend