Master Bathroom Remodel: Geddes

This project was completed in April 2010.

E-Mail to a Friend

February 15, 2010

Geddes-Floor-Plan

Here is the plan for the new master bathroom,
designed in collaboration with Jennifer Siegel.
We are altering the layout, and installing
all new fixtures and finishes.

Geddes-Exist-Sink

This corner will be redone with new cabinets and fixtures . . .

Geddes-Elev

. . . which can be seen in this elevation drawing.
The shower gets new tile and fixtures as well.

Geddes-Exist-Tub

The tub will be replaced with a second sink
and a new storage cabinet.  A new toilet will be
installed in the current location.

March 5, 2010

geddes-shower-studs

The space has been demoed back to studs,
and plumbing work has started.

geddes-plumbing

Here, the subfloor was been removed so that
new sink plumbing could be installed.

March 18, 2010

Geddes-tile-drywall

New drywall has been hung, and the
tile floor installation has been started.

Geddes-shower-tile

The shower tile has been installed, with an
alternating pattern of square and rectangular tiles.

March 31, 2010

Geddes-cabinet-install-1

Cabinet installation is proceeding.

Geddes-cabinet-install-2

On the other side of the room, the cabinets are already in.

April 7, 2010

geddes-countertop-2

After cabinets were finished, the countertop
and backsplash went in next.

geddes-countertop-1

Here, countertops are also installed,
as well as the vessel sink.

April 13, 2010

geddes-fin-sink

The finished sink area.

geddes-fin-shower

The finished shower, with the door installed.

geddes-client

Our happy client in brand new master bath.